Case StudyManufacturing·ERP

How a growing manufacturer replaced a 15-year-old ERP, on time in 11 months.

An ageing ERP system and a web of spreadsheets were holding the business back. Skillfi's fractional CIO chose the right platform, kept the implementation partner on track and brought every team along, so the new system went live on schedule and actually got used. It's how our fractional CIO service works: technology that makes the whole business run better.

Inventory accuracy
82%→98%
On timeLive in 11 months
−5 daysMonth-end close
60 → 4Spreadsheets in use
01

A business that outgrew its system years ago.

The company makes food packaging in two plants and had doubled in size in five years. Its ERP system was 15 years old, no longer supported and couldn't handle a second plant, so teams built more than 60 spreadsheets to fill the gaps.

Stock counts were wrong almost one time in five, so orders were promised that couldn't be shipped and materials were bought twice. Planning ran on a spreadsheet one person understood. Finance spent days stitching numbers together at month-end. A previous attempt to replace the ERP had stalled after a year with nothing live, and staff were sceptical it would ever happen.

15 yearsold and unsupported
60+spreadsheets filling the gaps
82%inventory accuracy

We'd already tried once and failed. Everyone assumed a new ERP was a project that never ends.

CEO, client
02

Choose carefully, manage the partner tightly and bring people with you.

Our fractional CIO owned the project from selection to go-live, acting for the business rather than the software vendor. Finance processes in the new system were designed with a fractional CFO.

Select

The right platform and partner

Requirements gathered from every team, three platforms scored through scripted demos and a partner chosen on manufacturing experience, not price alone.

Deliver

A partner held to milestones

Standard features first and few customisations, a fixed scope, payments tied to milestones and weekly progress reviews against the plan.

Adopt

People ready on day one

Champions in every team, hands-on training, three full practice runs before go-live and floor support for the first month.

The Engagement

11 months, step by step

From an ageing system and 60 spreadsheets to one platform the whole company runs on. Here's how the engagement unfolded.

  1. Month 1–2

    Requirements & selection

    Processes mapped with every team, three platforms tested through scripted demos and a clear winner chosen.

    3 platforms scored
  2. Month 2–3

    Partner & plan

    Implementation partner selected, scope fixed and payments tied to clear milestones.

    Fixed scope
  3. Month 3–7

    Design & build

    Purchasing, production planning, inventory, sales and finance set up on standard processes wherever possible.

    5 modules
  4. Month 6–9

    Data & testing

    15 years of data cleaned and moved, with three full practice runs of a real week in the new system.

    3 practice runs
  5. Month 8–10

    Training & readiness

    Champions trained first, then every user, with go-live checklists signed off by each team.

    310 people trained
  6. Month 11

    Go-live

    Both plants switched over on the planned date, with floor support and daily check-ins for the first month.

    Live on time
Inside the New ERP

One system, from order to cash

Every step of the business now runs in one place, with the spreadsheets that used to hold it together retired.

SellOrders

Promises you can keep

  • Live stock when quoting
  • Real delivery dates
  • Order tracking
PlanProduction

Both plants, one plan

  • Production scheduling
  • Material planning
  • Capacity by plant
StockInventory

Counts you can trust

  • Barcode scanning
  • Cycle counts
  • Reorder alerts
ReportFinance

Numbers without stitching

  • Costs by product
  • Faster month-end
  • Live dashboards
Every quarter: System health reviewUsage, data quality and improvement requests reviewed every quarter, so the ERP keeps up as the business grows.
Month 2 · Platform chosen Month 9 · 3 practice runs Month 11 · Live on time
The Results

Six months after go-live

Inventory accuracy

Old ERP & spreadsheets82%
New ERP with scanning98%
0%25%50%75%100%

So customer promises are based on stock that's really there.

Month-end close11 days→6 days
On-time deliveries84%→96%
Spreadsheets in use60+→4
Excess raw material stock—→−27%
Go-live datePlanned→Met
CE

After one failed attempt, we went live on the exact date we planned. Our stock numbers are finally right, and our teams run the business instead of their spreadsheets.

CEO, client
Your Turn

Has your business outgrown its systems?

Our fractional CIO will choose the right platform, hold your implementation partner to the plan and get your people ready, so your new system goes live on time and gets used. Want finance set up right from day one? Add a fractional CFO.

What we'd build for you
  • Requirements & platform selection
  • A partner held to milestones
  • Clean data & practice runs
  • Training & go-live support